Oracle issues force majeure notice on New Mexico Stargate data center

cloud-costs gpu-supply infrastructure reliability

Oracle has sent a force majeure notice — a legal clause excusing contractual obligations due to events outside a party's control — to Blue Owl Capital, the developer of Project Jupiter, a Stargate AI data center campus in New Mexico. The notice would allow Oracle to delay payments if the facility misses its 2028 target to come online, though Oracle publicly maintains the project remains on schedule and is not seeking to exit its tenant agreement.

Project Jupiter is a flagship site of the Stargate AI infrastructure initiative jointly announced by Oracle, OpenAI, and SoftBank alongside President Trump. The 2.45-gigawatt campus faces compounding setbacks: a gas pipeline from Energy Transfer has been delayed nearly six months to February 2027 after repeated permit rejections, and a separate air-quality permit for the Bloom Energy fuel cell system is still pending. The delays highlight growing risks in the buildout of large-scale AI compute infrastructure, where energy supply and regulatory hurdles are emerging as critical bottlenecks.

Analysis

Showing the shorter version.

Oracle filed a force majeure notice on Project Jupiter, its 2.45-gigawatt Stargate data center campus in New Mexico, developed by Blue Owl Capital. The notice gives Oracle the legal right to stop paying rent if the building isn't ready on time. Oracle's public statement says the project "remains on planned schedule." Both things cannot be fully true. You file force majeure paperwork when your lawyers see the schedule slipping, not when they're confident it holds.

The reason for the slip has nothing to do with chips or capital. The gas pipeline from Energy Transfer slid nearly six months, to February 2027, after permits were rejected more than once. The Bloom Energy fuel cell air permit is still pending. Two of the three power dependencies are unresolved, and permit chains compound: the pipeline has to close before the fuel-cell approval makes sense, and both have to clear before grid interconnect can finalize. A six-month slip at the front of that chain does not stay six months by the time it works through the rest.

For anyone who penciled in new Stargate capacity for 2027 or early 2028, the practical consequence is that announced gigawatts are not the same as capacity you can actually rent. Blackwell racks are too expensive to warehouse. They get rerouted to whatever building already has power flowing. If Project Jupiter slips, the compute earmarked for it goes somewhere else, and "somewhere else" is already scarce, because every hyperscaler is chasing the same short list of sites with power already connected.

The less-discussed risk is concentration. If this campus eventually hosts a large share of OpenAI's training and inference workload, then a regulatory hold or physical disruption at one New Mexico site stops being a capacity shortfall and becomes a service outage that runs through every product built on top of it. The force majeure notice accidentally traces a dependency chain, from OpenAI down to a pending state air permit, that no public reliability plan has mapped.

The call: Project Jupiter will not be fully operational by its 2028 target. Oracle or Blue Owl will publicly acknowledge a slip past 2028 by the time Oracle reports fiscal Q4 2028 earnings in June 2028. Confidence is medium. The permit record on this exact site is already one of repeated rejections; hitting 2028 cleanly requires every remaining approval to clear faster than the ones that already failed. That is the less likely path.